Time and Work
MCQs Math


Question:     Charles can finish a work in 19 days. Christopher can finish the same work in 20 days while Daniel can finish the work in 21 days. How long will it take to finish it if they work together?


Correct Answer  6 786/1199 days or 6.656 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Charles = 19 days

And, the number of days required to finish the same work by Christopher = 20 days

And, the number of days required to finish the same work by Daniel = 21 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 19 days the work is done by Charles = 1

∴ The work done by Charles in 1 day = 1/19

Similarly,

∵ In 20 days the work is done by Christopher = 1

∴ The work done by Christopher in 1 day = 1/20

Similarly,

∵ In 21 days the work is done by Daniel = 1

∴ The work done by Daniel in 1 day = 1/21 part

Now, the work done by Charles, Christopher, and Daniel together in 1 day

= Charles's 1 day work + Christopher's 1 day work + Daniel's 1 day work

= 1/19 + 1/20 + 1/21

= 420 + 399 + 380/7980

= 1199/7980 part of work

This means in 1 day, 1199/7980 part of work is done by Charles, Christopher and Daniel working together.

Now, the number of days required to finish 1199/7980 part of work by Charles, Christopher, and Daniel working together = 1

∴ the number of days required to finish the whole work (1 work) by Charles + Christopher + Daniel together

= 1/1199/7980

= 1 × 7980/1199 = 7980/1199 days

= 6 786/1199 days = or 6.656 days

Thus, Charles, Christopher, and Daniel working together will finish the total work (1 work) in 6 786/1199 days = or 6.656 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Charles = 19 days

And the number of days required to finish the same work by Christopher = 20 days

And the number of days required to finish the work by Daniel = 21 days

Thus, the number of days required to finish the work by Charles, Christopher, and Daniel together = ?

Here a = 19 days

And, b = 20 days

And, c = 21 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Charles, Christopher, and Daniel working together

= 19 × 20 × 21/19 × 20 + 19 × 21 + 20 × 21 days

= 7980/380 + 399 + 420 days

= 7980/1199 days

= 7980/1199 days

= 6 786/1199 days or 6.656

Thus, Charles, Christopher, and Daniel together will finish the work in 6 786/1199 days or 6.656 days Answer


Similar Questions

(1) Susan can finish a work in 14 days. Jessica can finish the same work in 15 days while Sarah can finish the work in 16 days. How long will it take to finish it if they work together?

(2) Amy can finish a work in 68 days. Shirley can finish the same work in 73 days while Anna can finish the work in 78 days. How long will it take to finish it if they work together?

(3) If Amy can finish the work in 68 days and Keith can finish the same work in 73 days, then in how many days both can finish the work together?

(4) If George can finish the work in 51 days and Dennis can finish the same work in 56 days, then in how many days both can finish the work together?

(5) If Sarah can finish the work in 22 days and Joshua can finish the same work in 27 days, then in how many days both can finish the work together?

(6) If Melissa can finish the work in 52 days and Jerry can finish the same work in 57 days, then in how many days both can finish the work together?

(7) If Jeffrey can finish the work in 61 days and Peter can finish the same work in 66 days, then in how many days both can finish the work together?

(8) If Betty can finish the work in 30 days and Jason can finish the same work in 35 days, then in how many days both can finish the work together?

(9) Melissa can finish a work in 48 days. Deborah can finish the same work in 49 days while Stephanie can finish the work in 50 days. How long will it take to finish it if they work together?

(10) If Kathleen can finish the work in 66 days and Jeremy can finish the same work in 71 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©