Time and Work
MCQs Math


Question:     Charles can finish a work in 19 days. Christopher can finish the same work in 20 days while Daniel can finish the work in 21 days. How long will it take to finish it if they work together?


Correct Answer  6 786/1199 days or 6.656 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Charles = 19 days

And, the number of days required to finish the same work by Christopher = 20 days

And, the number of days required to finish the same work by Daniel = 21 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 19 days the work is done by Charles = 1

∴ The work done by Charles in 1 day = 1/19

Similarly,

∵ In 20 days the work is done by Christopher = 1

∴ The work done by Christopher in 1 day = 1/20

Similarly,

∵ In 21 days the work is done by Daniel = 1

∴ The work done by Daniel in 1 day = 1/21 part

Now, the work done by Charles, Christopher, and Daniel together in 1 day

= Charles's 1 day work + Christopher's 1 day work + Daniel's 1 day work

= 1/19 + 1/20 + 1/21

= 420 + 399 + 380/7980

= 1199/7980 part of work

This means in 1 day, 1199/7980 part of work is done by Charles, Christopher and Daniel working together.

Now, the number of days required to finish 1199/7980 part of work by Charles, Christopher, and Daniel working together = 1

∴ the number of days required to finish the whole work (1 work) by Charles + Christopher + Daniel together

= 1/1199/7980

= 1 × 7980/1199 = 7980/1199 days

= 6 786/1199 days = or 6.656 days

Thus, Charles, Christopher, and Daniel working together will finish the total work (1 work) in 6 786/1199 days = or 6.656 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Charles = 19 days

And the number of days required to finish the same work by Christopher = 20 days

And the number of days required to finish the work by Daniel = 21 days

Thus, the number of days required to finish the work by Charles, Christopher, and Daniel together = ?

Here a = 19 days

And, b = 20 days

And, c = 21 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Charles, Christopher, and Daniel working together

= 19 × 20 × 21/19 × 20 + 19 × 21 + 20 × 21 days

= 7980/380 + 399 + 420 days

= 7980/1199 days

= 7980/1199 days

= 6 786/1199 days or 6.656

Thus, Charles, Christopher, and Daniel together will finish the work in 6 786/1199 days or 6.656 days Answer


Similar Questions

(1) Timothy can finish a work in 53 days. Edward can finish the same work in 58 days while Jason can finish the work in 63 days. How long will it take to finish it if they work together?

(2) If Melissa can finish the work in 52 days and Jerry can finish the same work in 57 days, then in how many days both can finish the work together?

(3) Jeffrey can finish a work in 61 days. Jacob can finish the same work in 66 days while Gary can finish the work in 71 days. How long will it take to finish it if they work together?

(4) Stephen can finish a work in 75 days. Justin can finish the same work in 80 days while Scott can finish the work in 85 days. How long will it take to finish it if they work together?

(5) If Ashley can finish the work in 33 days and Eric can finish the same work in 36 days, then in how many days both can finish the work together?

(6) Eric can finish a work in 71 days. Stephen can finish the same work in 76 days while Larry can finish the work in 81 days. How long will it take to finish it if they work together?

(7) If Robert can finish the work in 4 days and David can finish the same work in 8 days, then in how many days both can finish the work together?

(8) If Amanda can finish the work in 45 days and Patrick can finish the same work in 49 days, then in how many days both can finish the work together?

(9) If Mary can finish the work in 3 days and Michael can finish the same work in 7 days, then in how many days both can finish the work together?

(10) If Anthony can finish the work in 31 days and Jeffrey can finish the same work in 36 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©