Time and Work
MCQs Math


Question:     Margaret can finish a work in 28 days. Sandra can finish the same work in 29 days while Ashley can finish the work in 30 days. How long will it take to finish it if they work together?


Correct Answer  9 831/1261 days or 9.659 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Margaret = 28 days

And, the number of days required to finish the same work by Sandra = 29 days

And, the number of days required to finish the same work by Ashley = 30 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 28 days the work is done by Margaret = 1

∴ The work done by Margaret in 1 day = 1/28

Similarly,

∵ In 29 days the work is done by Sandra = 1

∴ The work done by Sandra in 1 day = 1/29

Similarly,

∵ In 30 days the work is done by Ashley = 1

∴ The work done by Ashley in 1 day = 1/30 part

Now, the work done by Margaret, Sandra, and Ashley together in 1 day

= Margaret's 1 day work + Sandra's 1 day work + Ashley's 1 day work

= 1/28 + 1/29 + 1/30

= 435 + 420 + 406/12180

= 1261/12180 part of work

This means in 1 day, 1261/12180 part of work is done by Margaret, Sandra and Ashley working together.

Now, the number of days required to finish 1261/12180 part of work by Margaret, Sandra, and Ashley working together = 1

∴ the number of days required to finish the whole work (1 work) by Margaret + Sandra + Ashley together

= 1/1261/12180

= 1 × 12180/1261 = 12180/1261 days

= 9 831/1261 days = or 9.659 days

Thus, Margaret, Sandra, and Ashley working together will finish the total work (1 work) in 9 831/1261 days = or 9.659 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Margaret = 28 days

And the number of days required to finish the same work by Sandra = 29 days

And the number of days required to finish the work by Ashley = 30 days

Thus, the number of days required to finish the work by Margaret, Sandra, and Ashley together = ?

Here a = 28 days

And, b = 29 days

And, c = 30 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Margaret, Sandra, and Ashley working together

= 28 × 29 × 30/28 × 29 + 28 × 30 + 29 × 30 days

= 24360/812 + 840 + 870 days

= 24360/2522 days

= 24360/2522 days

= 24360 ÷ 2/2522 ÷ 2 = 12180/1261 days

= 9 831/1261 days or 9.659

Thus, Margaret, Sandra, and Ashley together will finish the work in 9 831/1261 days or 9.659 days Answer


Similar Questions

(1) Joseph can finish a work in 19 days. Charles can finish the same work in 24 days while Christopher can finish the work in 29 days. How long will it take to finish it if they work together?

(2) If Robert can finish a work in 4 days and Bob can finish the same work in 6 days, then in how many days they both can finish the work working together?

(3) If Nicholas can finish the work in 69 days and Roger can finish the same work in 74 days, then in how many days both can finish the work together?

(4) Joshua can finish a work in 39 days. Kenneth can finish the same work in 40 days while Kevin can finish the work in 41 days. How long will it take to finish it if they work together?

(5) If Ashley can finish the work in 33 days and Eric can finish the same work in 36 days, then in how many days both can finish the work together?

(6) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 46 days, then in how many days both can finish the work together?

(7) If John can finish the work in 6 days and Richard can finish the same work in 10 days, then in how many days both can finish the work together?

(8) Raymond can finish a work in 97 days. Dennis can finish the same work in 102 days while Jerry can finish the work in 107 days. How long will it take to finish it if they work together?

(9) Susan can finish a work in 14 days. Jessica can finish the same work in 15 days while Sarah can finish the work in 16 days. How long will it take to finish it if they work together?

(10) If Sarah can finish the work in 19 days and Joshua can finish the same work in 22 days, then in how many days both can finish the work together?