Time and Work
MCQs Math


Question:     Donald can finish a work in 31 days. Steven can finish the same work in 32 days while Paul can finish the work in 33 days. How long will it take to finish it if they work together?


Correct Answer  10 2026/3071 days or 10.66 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Donald = 31 days

And, the number of days required to finish the same work by Steven = 32 days

And, the number of days required to finish the same work by Paul = 33 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 31 days the work is done by Donald = 1

∴ The work done by Donald in 1 day = 1/31

Similarly,

∵ In 32 days the work is done by Steven = 1

∴ The work done by Steven in 1 day = 1/32

Similarly,

∵ In 33 days the work is done by Paul = 1

∴ The work done by Paul in 1 day = 1/33 part

Now, the work done by Donald, Steven, and Paul together in 1 day

= Donald's 1 day work + Steven's 1 day work + Paul's 1 day work

= 1/31 + 1/32 + 1/33

= 1056 + 1023 + 992/32736

= 3071/32736 part of work

This means in 1 day, 3071/32736 part of work is done by Donald, Steven and Paul working together.

Now, the number of days required to finish 3071/32736 part of work by Donald, Steven, and Paul working together = 1

∴ the number of days required to finish the whole work (1 work) by Donald + Steven + Paul together

= 1/3071/32736

= 1 × 32736/3071 = 32736/3071 days

= 10 2026/3071 days = or 10.66 days

Thus, Donald, Steven, and Paul working together will finish the total work (1 work) in 10 2026/3071 days = or 10.66 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Donald = 31 days

And the number of days required to finish the same work by Steven = 32 days

And the number of days required to finish the work by Paul = 33 days

Thus, the number of days required to finish the work by Donald, Steven, and Paul together = ?

Here a = 31 days

And, b = 32 days

And, c = 33 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Donald, Steven, and Paul working together

= 31 × 32 × 33/31 × 32 + 31 × 33 + 32 × 33 days

= 32736/992 + 1023 + 1056 days

= 32736/3071 days

= 32736/3071 days

= 10 2026/3071 days or 10.66

Thus, Donald, Steven, and Paul together will finish the work in 10 2026/3071 days or 10.66 days Answer


Similar Questions

(1) If Robert can finish the work in 26 days and David can finish the same work in 42 days, then in how many days both can finish the work together?

(2) If Brian can finish the work in 46 days and Raymond can finish the same work in 50 days, then in how many days both can finish the work together?

(3) If Charles can finish the work in 23 days and Kenneth can finish the same work in 28 days, then in how many days both can finish the work together?

(4) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?

(5) If Donna can finish the work in 39 days and Brandon can finish the same work in 43 days, then in how many days both can finish the work together?

(6) Joshua can finish a work in 43 days. Kevin can finish the same work in 48 days while Brian can finish the work in 53 days. How long will it take to finish it if they work together?

(7) If Sarah can finish the work in 19 days and Joshua can finish the same work in 22 days, then in how many days both can finish the work together?

(8) Nancy can finish a work in 24 days. Betty can finish the same work in 25 days while Margaret can finish the work in 26 days. How long will it take to finish it if they work together?

(9) David can finish a work in 9 days. William can finish the same work in 10 days while Richard can finish the work in 11 days. How long will it take to finish it if they work together?

(10) Robert can finish a work in 7 days. Michael can finish the same work in 12 days while David can finish the work in 17 days. How long will it take to finish it if they work together?