Time and Work
MCQs Math


Question:     Ashley can finish a work in 32 days. Kimberly can finish the same work in 33 days while Emily can finish the work in 34 days. How long will it take to finish it if they work together?


Correct Answer  10 1622/1633 days or 10.993 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Ashley = 32 days

And, the number of days required to finish the same work by Kimberly = 33 days

And, the number of days required to finish the same work by Emily = 34 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 32 days the work is done by Ashley = 1

∴ The work done by Ashley in 1 day = 1/32

Similarly,

∵ In 33 days the work is done by Kimberly = 1

∴ The work done by Kimberly in 1 day = 1/33

Similarly,

∵ In 34 days the work is done by Emily = 1

∴ The work done by Emily in 1 day = 1/34 part

Now, the work done by Ashley, Kimberly, and Emily together in 1 day

= Ashley's 1 day work + Kimberly's 1 day work + Emily's 1 day work

= 1/32 + 1/33 + 1/34

= 561 + 544 + 528/17952

= 1633/17952 part of work

This means in 1 day, 1633/17952 part of work is done by Ashley, Kimberly and Emily working together.

Now, the number of days required to finish 1633/17952 part of work by Ashley, Kimberly, and Emily working together = 1

∴ the number of days required to finish the whole work (1 work) by Ashley + Kimberly + Emily together

= 1/1633/17952

= 1 × 17952/1633 = 17952/1633 days

= 10 1622/1633 days = or 10.993 days

Thus, Ashley, Kimberly, and Emily working together will finish the total work (1 work) in 10 1622/1633 days = or 10.993 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Ashley = 32 days

And the number of days required to finish the same work by Kimberly = 33 days

And the number of days required to finish the work by Emily = 34 days

Thus, the number of days required to finish the work by Ashley, Kimberly, and Emily together = ?

Here a = 32 days

And, b = 33 days

And, c = 34 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Ashley, Kimberly, and Emily working together

= 32 × 33 × 34/32 × 33 + 32 × 34 + 33 × 34 days

= 35904/1056 + 1088 + 1122 days

= 35904/3266 days

= 35904/3266 days

= 35904 ÷ 2/3266 ÷ 2 = 17952/1633 days

= 10 1622/1633 days or 10.993

Thus, Ashley, Kimberly, and Emily together will finish the work in 10 1622/1633 days or 10.993 days Answer


Similar Questions

(1) Donna can finish a work in 42 days. Carol can finish the same work in 47 days while Amanda can finish the work in 52 days. How long will it take to finish it if they work together?

(2) Melissa can finish a work in 52 days. Stephanie can finish the same work in 57 days while Rebecca can finish the work in 62 days. How long will it take to finish it if they work together?

(3) If Donna can finish the work in 39 days and Brandon can finish the same work in 42 days, then in how many days both can finish the work together?

(4) If Jack can finish the work in 99 days and Bobby can finish the same work in 104 days, then in how many days both can finish the work together?

(5) If Janet can finish the work in 98 days and Russell can finish the same work in 103 days, then in how many days both can finish the work together?

(6) Elizabeth can finish a work in 14 days. Susan can finish the same work in 19 days while Jessica can finish the work in 24 days. How long will it take to finish it if they work together?

(7) Christine can finish a work in 90 days. Rachel can finish the same work in 95 days while Carolyn can finish the work in 100 days. How long will it take to finish it if they work together?

(8) If Catherine can finish the work in 100 days and Mason can finish the same work in 105 days, then in how many days both can finish the work together?

(9) Christopher can finish a work in 25 days. Matthew can finish the same work in 30 days while Anthony can finish the work in 35 days. How long will it take to finish it if they work together?

(10) If Ronald can finish the work in 55 days and Jose can finish the same work in 60 days, then in how many days both can finish the work together?