Time and Work
MCQs Math


Question:     Steven can finish a work in 33 days. Paul can finish the same work in 34 days while Andrew can finish the work in 35 days. How long will it take to finish it if they work together?


Correct Answer  11 1133/3467 days or 11.327 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Steven = 33 days

And, the number of days required to finish the same work by Paul = 34 days

And, the number of days required to finish the same work by Andrew = 35 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 33 days the work is done by Steven = 1

∴ The work done by Steven in 1 day = 1/33

Similarly,

∵ In 34 days the work is done by Paul = 1

∴ The work done by Paul in 1 day = 1/34

Similarly,

∵ In 35 days the work is done by Andrew = 1

∴ The work done by Andrew in 1 day = 1/35 part

Now, the work done by Steven, Paul, and Andrew together in 1 day

= Steven's 1 day work + Paul's 1 day work + Andrew's 1 day work

= 1/33 + 1/34 + 1/35

= 1190 + 1155 + 1122/39270

= 3467/39270 part of work

This means in 1 day, 3467/39270 part of work is done by Steven, Paul and Andrew working together.

Now, the number of days required to finish 3467/39270 part of work by Steven, Paul, and Andrew working together = 1

∴ the number of days required to finish the whole work (1 work) by Steven + Paul + Andrew together

= 1/3467/39270

= 1 × 39270/3467 = 39270/3467 days

= 11 1133/3467 days = or 11.327 days

Thus, Steven, Paul, and Andrew working together will finish the total work (1 work) in 11 1133/3467 days = or 11.327 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Steven = 33 days

And the number of days required to finish the same work by Paul = 34 days

And the number of days required to finish the work by Andrew = 35 days

Thus, the number of days required to finish the work by Steven, Paul, and Andrew together = ?

Here a = 33 days

And, b = 34 days

And, c = 35 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Steven, Paul, and Andrew working together

= 33 × 34 × 35/33 × 34 + 33 × 35 + 34 × 35 days

= 39270/1122 + 1155 + 1190 days

= 39270/3467 days

= 39270/3467 days

= 11 1133/3467 days or 11.327

Thus, Steven, Paul, and Andrew together will finish the work in 11 1133/3467 days or 11.327 days Answer


Similar Questions

(1) If Michael can finish the work in 30 days and Thomas can finish the same work in 46 days, then in how many days both can finish the work together?

(2) If Amanda can finish the work in 48 days and Patrick can finish the same work in 53 days, then in how many days both can finish the work together?

(3) If Andrew can finish the work in 38 days and Scott can finish the same work in 41 days, then in how many days both can finish the work together?

(4) Andrew can finish a work in 41 days. Kenneth can finish the same work in 46 days while Kevin can finish the work in 51 days. How long will it take to finish it if they work together?

(5) Carolyn can finish a work in 96 days. Catherine can finish the same work in 101 days while Maria can finish the work in 106 days. How long will it take to finish it if they work together?

(6) If Anthony can finish the work in 31 days and Jeffrey can finish the same work in 36 days, then in how many days both can finish the work together?

(7) If Kimberly can finish the work in 38 days and Stephen can finish the same work in 43 days, then in how many days both can finish the work together?

(8) If William can finish the work in 12 days and Matthew can finish the same work in 15 days, then in how many days both can finish the work together?

(9) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?

(10) Jack can finish a work in 99 days. Jerry can finish the same work in 104 days while Tyler can finish the work in 109 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©