Time and Work
MCQs Math


Question:     Joshua can finish a work in 39 days. Kenneth can finish the same work in 40 days while Kevin can finish the work in 41 days. How long will it take to finish it if they work together?


Correct Answer  13 1573/4799 days or 13.328 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Joshua = 39 days

And, the number of days required to finish the same work by Kenneth = 40 days

And, the number of days required to finish the same work by Kevin = 41 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 39 days the work is done by Joshua = 1

∴ The work done by Joshua in 1 day = 1/39

Similarly,

∵ In 40 days the work is done by Kenneth = 1

∴ The work done by Kenneth in 1 day = 1/40

Similarly,

∵ In 41 days the work is done by Kevin = 1

∴ The work done by Kevin in 1 day = 1/41 part

Now, the work done by Joshua, Kenneth, and Kevin together in 1 day

= Joshua's 1 day work + Kenneth's 1 day work + Kevin's 1 day work

= 1/39 + 1/40 + 1/41

= 1640 + 1599 + 1560/63960

= 4799/63960 part of work

This means in 1 day, 4799/63960 part of work is done by Joshua, Kenneth and Kevin working together.

Now, the number of days required to finish 4799/63960 part of work by Joshua, Kenneth, and Kevin working together = 1

∴ the number of days required to finish the whole work (1 work) by Joshua + Kenneth + Kevin together

= 1/4799/63960

= 1 × 63960/4799 = 63960/4799 days

= 13 1573/4799 days = or 13.328 days

Thus, Joshua, Kenneth, and Kevin working together will finish the total work (1 work) in 13 1573/4799 days = or 13.328 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Joshua = 39 days

And the number of days required to finish the same work by Kenneth = 40 days

And the number of days required to finish the work by Kevin = 41 days

Thus, the number of days required to finish the work by Joshua, Kenneth, and Kevin together = ?

Here a = 39 days

And, b = 40 days

And, c = 41 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Joshua, Kenneth, and Kevin working together

= 39 × 40 × 41/39 × 40 + 39 × 41 + 40 × 41 days

= 63960/1560 + 1599 + 1640 days

= 63960/4799 days

= 63960/4799 days

= 13 1573/4799 days or 13.328

Thus, Joshua, Kenneth, and Kevin together will finish the work in 13 1573/4799 days or 13.328 days Answer


Similar Questions

(1) If Linda can finish the work in 9 days and Charles can finish the same work in 13 days, then in how many days both can finish the work together?

(2) Carol can finish a work in 42 days. Amanda can finish the same work in 43 days while Dorothy can finish the work in 44 days. How long will it take to finish it if they work together?

(3) If Deborah can finish the work in 54 days and Aaron can finish the same work in 59 days, then in how many days both can finish the work together?

(4) Benjamin can finish a work in 85 days. Gregory can finish the same work in 90 days while Alexander can finish the work in 95 days. How long will it take to finish it if they work together?

(5) If George can finish the work in 48 days and Dennis can finish the same work in 51 days, then in how many days both can finish the work together?

(6) Charles can finish a work in 19 days. Christopher can finish the same work in 20 days while Daniel can finish the work in 21 days. How long will it take to finish it if they work together?

(7) Jonathan can finish a work in 73 days. Larry can finish the same work in 78 days while Justin can finish the work in 83 days. How long will it take to finish it if they work together?

(8) If Brian can finish the work in 46 days and Raymond can finish the same work in 49 days, then in how many days both can finish the work together?

(9) Rebecca can finish a work in 58 days. Laura can finish the same work in 63 days while Cynthia can finish the work in 68 days. How long will it take to finish it if they work together?

(10) If Stephanie can finish the work in 56 days and Adam can finish the same work in 61 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©