Time and Work
MCQs Math


Question:     Joshua can finish a work in 39 days. Kenneth can finish the same work in 40 days while Kevin can finish the work in 41 days. How long will it take to finish it if they work together?


Correct Answer  13 1573/4799 days or 13.328 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Joshua = 39 days

And, the number of days required to finish the same work by Kenneth = 40 days

And, the number of days required to finish the same work by Kevin = 41 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 39 days the work is done by Joshua = 1

∴ The work done by Joshua in 1 day = 1/39

Similarly,

∵ In 40 days the work is done by Kenneth = 1

∴ The work done by Kenneth in 1 day = 1/40

Similarly,

∵ In 41 days the work is done by Kevin = 1

∴ The work done by Kevin in 1 day = 1/41 part

Now, the work done by Joshua, Kenneth, and Kevin together in 1 day

= Joshua's 1 day work + Kenneth's 1 day work + Kevin's 1 day work

= 1/39 + 1/40 + 1/41

= 1640 + 1599 + 1560/63960

= 4799/63960 part of work

This means in 1 day, 4799/63960 part of work is done by Joshua, Kenneth and Kevin working together.

Now, the number of days required to finish 4799/63960 part of work by Joshua, Kenneth, and Kevin working together = 1

∴ the number of days required to finish the whole work (1 work) by Joshua + Kenneth + Kevin together

= 1/4799/63960

= 1 × 63960/4799 = 63960/4799 days

= 13 1573/4799 days = or 13.328 days

Thus, Joshua, Kenneth, and Kevin working together will finish the total work (1 work) in 13 1573/4799 days = or 13.328 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Joshua = 39 days

And the number of days required to finish the same work by Kenneth = 40 days

And the number of days required to finish the work by Kevin = 41 days

Thus, the number of days required to finish the work by Joshua, Kenneth, and Kevin together = ?

Here a = 39 days

And, b = 40 days

And, c = 41 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Joshua, Kenneth, and Kevin working together

= 39 × 40 × 41/39 × 40 + 39 × 41 + 40 × 41 days

= 63960/1560 + 1599 + 1640 days

= 63960/4799 days

= 63960/4799 days

= 13 1573/4799 days or 13.328

Thus, Joshua, Kenneth, and Kevin together will finish the work in 13 1573/4799 days or 13.328 days Answer


Similar Questions

(1) If Daniel can finish the work in 24 days and Timothy can finish the same work in 27 days, then in how many days both can finish the work together?

(2) If Ronald can finish the work in 55 days and Jose can finish the same work in 60 days, then in how many days both can finish the work together?

(3) If Carol can finish the work in 43 days and Alexander can finish the same work in 46 days, then in how many days both can finish the work together?

(4) If Patricia can finish the work in 5 days and William can finish the same work in 9 days, then in how many days both can finish the work together?

(5) Jacob can finish a work in 65 days. Nicholas can finish the same work in 70 days while Eric can finish the work in 75 days. How long will it take to finish it if they work together?

(6) Donna can finish a work in 42 days. Carol can finish the same work in 47 days while Amanda can finish the work in 52 days. How long will it take to finish it if they work together?

(7) If Samantha can finish the work in 86 days and Logan can finish the same work in 91 days, then in how many days both can finish the work together?

(8) Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?

(9) If Sarah can finish the work in 19 days and Joshua can finish the same work in 22 days, then in how many days both can finish the work together?

(10) Sarah can finish a work in 18 days. Karen can finish the same work in 19 days while Lisa can finish the work in 20 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©