Question:     Kevin can finish a work in 43 days. Brian can finish the same work in 44 days while George can finish the work in 45 days. How long will it take to finish it if they work together?


Correct Answer  14 3842/5807 days or 14.662 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Kevin = 43 days

And, the number of days required to finish the same work by Brian = 44 days

And, the number of days required to finish the same work by George = 45 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 43 days the work is done by Kevin = 1

∴ The work done by Kevin in 1 day = 1/43

Similarly,

∵ In 44 days the work is done by Brian = 1

∴ The work done by Brian in 1 day = 1/44

Similarly,

∵ In 45 days the work is done by George = 1

∴ The work done by George in 1 day = 1/45 part

Now, the work done by Kevin, Brian, and George together in 1 day

= Kevin's 1 day work + Brian's 1 day work + George's 1 day work

= 1/43 + 1/44 + 1/45

= 1980 + 1935 + 1892/85140

= 5807/85140 part of work

This means in 1 day, 5807/85140 part of work is done by Kevin, Brian and George working together.

Now, the number of days required to finish 5807/85140 part of work by Kevin, Brian, and George working together = 1

∴ the number of days required to finish the whole work (1 work) by Kevin + Brian + George together

= 1/5807/85140

= 1 × 85140/5807 = 85140/5807 days

= 14 3842/5807 days = or 14.662 days

Thus, Kevin, Brian, and George working together will finish the total work (1 work) in 14 3842/5807 days = or 14.662 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Kevin = 43 days

And the number of days required to finish the same work by Brian = 44 days

And the number of days required to finish the work by George = 45 days

Thus, the number of days required to finish the work by Kevin, Brian, and George together = ?

Here a = 43 days

And, b = 44 days

And, c = 45 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Kevin, Brian, and George working together

= 43 × 44 × 45/43 × 44 + 43 × 45 + 44 × 45 days

= 85140/1892 + 1935 + 1980 days

= 85140/5807 days

= 85140/5807 days

= 14 3842/5807 days or 14.662

Thus, Kevin, Brian, and George together will finish the work in 14 3842/5807 days or 14.662 days Answer


Similar Questions

(1) Robert can finish a work in 3 days. John can finish the same work in 4 days while Michael can finish the work in 5 days. How long will it take to finish it if they work together?

(2) If Annie can finish a work in 5 days and Bobby can finish the same work in 10 days, then in how many days they both can finish the work working together?

(3) Samuel can finish a work in 87 days. Alexander can finish the same work in 92 days while Frank can finish the work in 97 days. How long will it take to finish it if they work together?

(4) Jonathan can finish a work in 73 days. Larry can finish the same work in 78 days while Justin can finish the work in 83 days. How long will it take to finish it if they work together?

(5) If Kevin can finish the work in 44 days and Frank can finish the same work in 47 days, then in how many days both can finish the work together?

(6) Edward can finish a work in 57 days. Jeffrey can finish the same work in 62 days while Ryan can finish the work in 67 days. How long will it take to finish it if they work together?

(7) Thomas can finish a work in 17 days. Charles can finish the same work in 18 days while Christopher can finish the work in 19 days. How long will it take to finish it if they work together?

(8) Larry can finish a work in 77 days. Scott can finish the same work in 82 days while Brandon can finish the work in 87 days. How long will it take to finish it if they work together?

(9) If Timothy can finish the work in 53 days and Tyler can finish the same work in 58 days, then in how many days both can finish the work together?

(10) Ryan can finish a work in 63 days. Gary can finish the same work in 68 days while Nicholas can finish the work in 73 days. How long will it take to finish it if they work together?