Question:     Brian can finish a work in 45 days. George can finish the same work in 46 days while Timothy can finish the work in 47 days. How long will it take to finish it if they work together?


Correct Answer  15 2085/6347 days or 15.329 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Brian = 45 days

And, the number of days required to finish the same work by George = 46 days

And, the number of days required to finish the same work by Timothy = 47 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 45 days the work is done by Brian = 1

∴ The work done by Brian in 1 day = 1/45

Similarly,

∵ In 46 days the work is done by George = 1

∴ The work done by George in 1 day = 1/46

Similarly,

∵ In 47 days the work is done by Timothy = 1

∴ The work done by Timothy in 1 day = 1/47 part

Now, the work done by Brian, George, and Timothy together in 1 day

= Brian's 1 day work + George's 1 day work + Timothy's 1 day work

= 1/45 + 1/46 + 1/47

= 2162 + 2115 + 2070/97290

= 6347/97290 part of work

This means in 1 day, 6347/97290 part of work is done by Brian, George and Timothy working together.

Now, the number of days required to finish 6347/97290 part of work by Brian, George, and Timothy working together = 1

∴ the number of days required to finish the whole work (1 work) by Brian + George + Timothy together

= 1/6347/97290

= 1 × 97290/6347 = 97290/6347 days

= 15 2085/6347 days = or 15.329 days

Thus, Brian, George, and Timothy working together will finish the total work (1 work) in 15 2085/6347 days = or 15.329 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Brian = 45 days

And the number of days required to finish the same work by George = 46 days

And the number of days required to finish the work by Timothy = 47 days

Thus, the number of days required to finish the work by Brian, George, and Timothy together = ?

Here a = 45 days

And, b = 46 days

And, c = 47 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Brian, George, and Timothy working together

= 45 × 46 × 47/45 × 46 + 45 × 47 + 46 × 47 days

= 97290/2070 + 2115 + 2162 days

= 97290/6347 days

= 97290/6347 days

= 15 2085/6347 days or 15.329

Thus, Brian, George, and Timothy together will finish the work in 15 2085/6347 days or 15.329 days Answer


Similar Questions

(1) Patricia can finish a work in 4 days. Jennifer can finish the same work in 5 days while Linda can finish the work in 6 days. How long will it take to finish it if they work together?

(2) Betty can finish a work in 26 days. Margaret can finish the same work in 27 days while Sandra can finish the work in 28 days. How long will it take to finish it if they work together?

(3) Charles can finish a work in 23 days. Daniel can finish the same work in 28 days while Matthew can finish the work in 33 days. How long will it take to finish it if they work together?

(4) Carolyn can finish a work in 96 days. Catherine can finish the same work in 101 days while Maria can finish the work in 106 days. How long will it take to finish it if they work together?

(5) George can finish a work in 47 days. Timothy can finish the same work in 48 days while Ronald can finish the work in 49 days. How long will it take to finish it if they work together?

(6) Susan can finish a work in 14 days. Jessica can finish the same work in 15 days while Sarah can finish the work in 16 days. How long will it take to finish it if they work together?

(7) Scott can finish a work in 81 days. Benjamin can finish the same work in 86 days while Samuel can finish the work in 91 days. How long will it take to finish it if they work together?

(8) Anthony can finish a work in 27 days. Mark can finish the same work in 28 days while Donald can finish the work in 29 days. How long will it take to finish it if they work together?

(9) Eric can finish a work in 71 days. Stephen can finish the same work in 76 days while Larry can finish the work in 81 days. How long will it take to finish it if they work together?

(10) If Sarah can finish the work in 22 days and Joshua can finish the same work in 27 days, then in how many days both can finish the work together?