Time and Work
MCQs Math


Question:     George can finish a work in 47 days. Timothy can finish the same work in 48 days while Ronald can finish the work in 49 days. How long will it take to finish it if they work together?


Correct Answer  15 6879/6911 days or 15.995 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by George = 47 days

And, the number of days required to finish the same work by Timothy = 48 days

And, the number of days required to finish the same work by Ronald = 49 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 47 days the work is done by George = 1

∴ The work done by George in 1 day = 1/47

Similarly,

∵ In 48 days the work is done by Timothy = 1

∴ The work done by Timothy in 1 day = 1/48

Similarly,

∵ In 49 days the work is done by Ronald = 1

∴ The work done by Ronald in 1 day = 1/49 part

Now, the work done by George, Timothy, and Ronald together in 1 day

= George's 1 day work + Timothy's 1 day work + Ronald's 1 day work

= 1/47 + 1/48 + 1/49

= 2352 + 2303 + 2256/110544

= 6911/110544 part of work

This means in 1 day, 6911/110544 part of work is done by George, Timothy and Ronald working together.

Now, the number of days required to finish 6911/110544 part of work by George, Timothy, and Ronald working together = 1

∴ the number of days required to finish the whole work (1 work) by George + Timothy + Ronald together

= 1/6911/110544

= 1 × 110544/6911 = 110544/6911 days

= 15 6879/6911 days = or 15.995 days

Thus, George, Timothy, and Ronald working together will finish the total work (1 work) in 15 6879/6911 days = or 15.995 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by George = 47 days

And the number of days required to finish the same work by Timothy = 48 days

And the number of days required to finish the work by Ronald = 49 days

Thus, the number of days required to finish the work by George, Timothy, and Ronald together = ?

Here a = 47 days

And, b = 48 days

And, c = 49 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when George, Timothy, and Ronald working together

= 47 × 48 × 49/47 × 48 + 47 × 49 + 48 × 49 days

= 110544/2256 + 2303 + 2352 days

= 110544/6911 days

= 110544/6911 days

= 15 6879/6911 days or 15.995

Thus, George, Timothy, and Ronald together will finish the work in 15 6879/6911 days or 15.995 days Answer


Similar Questions

(1) If Alexander can finish the work in 91 days and Wayne can finish the same work in 96 days, then in how many days both can finish the work together?

(2) Kimberly can finish a work in 34 days. Emily can finish the same work in 35 days while Donna can finish the work in 36 days. How long will it take to finish it if they work together?

(3) Samuel can finish a work in 87 days. Alexander can finish the same work in 92 days while Frank can finish the work in 97 days. How long will it take to finish it if they work together?

(4) If Patricia can finish the work in 5 days and William can finish the same work in 8 days, then in how many days both can finish the work together?

(5) If Betty can finish the work in 27 days and Jason can finish the same work in 31 days, then in how many days both can finish the work together?

(6) If Nicholas can finish the work in 69 days and Roger can finish the same work in 74 days, then in how many days both can finish the work together?

(7) Edward can finish a work in 57 days. Jeffrey can finish the same work in 62 days while Ryan can finish the work in 67 days. How long will it take to finish it if they work together?

(8) Andrew can finish a work in 37 days. Joshua can finish the same work in 38 days while Kenneth can finish the work in 39 days. How long will it take to finish it if they work together?

(9) Carol can finish a work in 42 days. Amanda can finish the same work in 43 days while Dorothy can finish the work in 44 days. How long will it take to finish it if they work together?

(10) If Nancy can finish the work in 28 days and Ronald can finish the same work in 33 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©