Time and Work
MCQs Math


Question:     George can finish a work in 47 days. Timothy can finish the same work in 48 days while Ronald can finish the work in 49 days. How long will it take to finish it if they work together?


Correct Answer  15 6879/6911 days or 15.995 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by George = 47 days

And, the number of days required to finish the same work by Timothy = 48 days

And, the number of days required to finish the same work by Ronald = 49 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 47 days the work is done by George = 1

∴ The work done by George in 1 day = 1/47

Similarly,

∵ In 48 days the work is done by Timothy = 1

∴ The work done by Timothy in 1 day = 1/48

Similarly,

∵ In 49 days the work is done by Ronald = 1

∴ The work done by Ronald in 1 day = 1/49 part

Now, the work done by George, Timothy, and Ronald together in 1 day

= George's 1 day work + Timothy's 1 day work + Ronald's 1 day work

= 1/47 + 1/48 + 1/49

= 2352 + 2303 + 2256/110544

= 6911/110544 part of work

This means in 1 day, 6911/110544 part of work is done by George, Timothy and Ronald working together.

Now, the number of days required to finish 6911/110544 part of work by George, Timothy, and Ronald working together = 1

∴ the number of days required to finish the whole work (1 work) by George + Timothy + Ronald together

= 1/6911/110544

= 1 × 110544/6911 = 110544/6911 days

= 15 6879/6911 days = or 15.995 days

Thus, George, Timothy, and Ronald working together will finish the total work (1 work) in 15 6879/6911 days = or 15.995 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by George = 47 days

And the number of days required to finish the same work by Timothy = 48 days

And the number of days required to finish the work by Ronald = 49 days

Thus, the number of days required to finish the work by George, Timothy, and Ronald together = ?

Here a = 47 days

And, b = 48 days

And, c = 49 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when George, Timothy, and Ronald working together

= 47 × 48 × 49/47 × 48 + 47 × 49 + 48 × 49 days

= 110544/2256 + 2303 + 2352 days

= 110544/6911 days

= 110544/6911 days

= 15 6879/6911 days or 15.995

Thus, George, Timothy, and Ronald together will finish the work in 15 6879/6911 days or 15.995 days Answer


Similar Questions

(1) Dorothy can finish a work in 46 days. Melissa can finish the same work in 47 days while Deborah can finish the work in 48 days. How long will it take to finish it if they work together?

(2) Elizabeth can finish a work in 14 days. Susan can finish the same work in 19 days while Jessica can finish the work in 24 days. How long will it take to finish it if they work together?

(3) If Mary can finish the work in 25 days and Michael can finish the same work in 41 days, then in how many days both can finish the work together?

(4) Patrick can finish a work in 95 days. Jack can finish the same work in 100 days while Dennis can finish the work in 105 days. How long will it take to finish it if they work together?

(5) David can finish a work in 13 days. Richard can finish the same work in 18 days while Joseph can finish the work in 23 days. How long will it take to finish it if they work together?

(6) If Amanda can finish the work in 45 days and Patrick can finish the same work in 48 days, then in how many days both can finish the work together?

(7) Patricia can finish a work in 4 days. Jennifer can finish the same work in 5 days while Linda can finish the work in 6 days. How long will it take to finish it if they work together?

(8) Kimberly can finish a work in 38 days. Donna can finish the same work in 43 days while Michelle can finish the work in 48 days. How long will it take to finish it if they work together?

(9) If Mark can finish the work in 30 days and Jacob can finish the same work in 34 days, then in how many days both can finish the work together?

(10) If Myra can finish the work in 25 days and Sophia can finish the same work in 15 days, then in how many days they both can finish the work working together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©